Services Over 400 Amps & Other Pre-Inspections

Learn more about pre-inspections.

Two weeks’ notice is required for an inspection of the following installations prior to concealment, operation and/or utility connection. The contractor may be requested to be present for:

  • Main service and or feeders where ampacity is over 400A
  • All renewable energy systems installations
  • Sewage lift and treatment facilities
  • Class A, B and C health care facilities as indicated by the current edition of the Z32 Standard, including identification of the patient care areas (See Section 24 in the Saskatchewan Interpretations for definitions)
  • Irrigation systems*
  • Marinas, wharves, docking facilities, fixed/floating piers and boathouses
  • Generator systems over 12 KW
  • Any other installation as deemed necessary by the Electrical Inspections department (e.g., large renovations of public buildings)

*Requirements taken from Saskatchewan Interpretations, Section 2-012

To facilitate the inspection of the installations, contractor photos can be attached to the permit in the GEIS Permit System or available at the time of the inspection to show the wiring installation, grounding connection and bonding of the equipment and installation of the equipment.

For further information, please contact the inspector for your district.